In short
In Spain the technical documentation of a demolition – proyecto or memoria técnica, estudio de seguridad y salud and estudio de gestión de residuos – is drafted and signed by a técnico competente; its scope depends on the job and on each town hall. The contractor prepares its own plan de seguridad y salud and plan de gestión de residuos from those studies. Whether your job needs a full proyecto or a memoria técnica is decided case by case (to be verified with your técnico and town hall).

Contents
- Why does a demolition need signed technical documents?
- The documents in a demolition file, one by one
- Proyecto or memoria técnica: which one do you need?
- What does the dirección facultativa do during the works?
- When is a safety coordinator needed?
- What the contractor does – and does not – sign
- How to find and brief a técnico from abroad
- Five misunderstandings about signatures and responsibility
- Examples: what documentation different jobs tend to involve
- Frequently asked questions
Why does a demolition need signed technical documents?
Because taking a building down safely is engineering work. The técnico has to state what the structure is, in what order it can be dismantled without collapse risk, how neighbouring buildings and the street are protected, and what happens to the waste. A town hall cannot accept a declaración responsable or grant a licence without that information, and the contractor needs it to plan the job.
In Spain this documentation is drafted and signed by a técnico competente – a qualified professional authorised to sign that type of work. Which professional qualification is competent for a given demolition is not something a contractor decides; your técnico and their professional association can confirm it for your case.
The documents in a demolition file, one by one
A demolition file brings together documents from two sides: the owner's técnico and the contractor.
| Document | Who prepares and signs it | What it is for |
|---|---|---|
| Proyecto or memoria técnica de demolición | Técnico competente | Describes the building, the demolition method, the sequence and protection measures |
| Certificado técnico | Técnico competente | Requested by some ordinances (Málaga city, for example) alongside the declaración responsable |
| Estudio de seguridad y salud or estudio básico | Técnico competente | Identifies risks and preventive measures for the works (Real Decreto 1627/1997) |
| Estudio de gestión de residuos | Included in the project by the promotor and técnico | Estimates the waste and how it will be managed (Real Decreto 105/2008) |
| Plan de seguridad y salud | Contractor | Adapts the safety study to the contractor's own methods and equipment |
| Plan de gestión de residuos | Contractor (as poseedor of the waste) | Sets how the contractor sorts and delivers the waste; approved by the dirección facultativa |
| Plan de trabajo de amianto | RERA-registered company | Required only if asbestos is present; approved by the provincial labour authority |
The scope of each document depends on the job and on what each town hall asks for. A small outbuilding on a finca and a four-storey block in a city centre do not need the same depth of documentation.
Proyecto or memoria técnica: which one do you need?
Both are signed technical documents describing the demolition. A proyecto is the more complete format; a memoria técnica is a lighter description. Málaga city's ordinance, for example, accepts either a proyecto or a memoria técnica signed by a técnico competente, plus a certificado técnico, for a declaración responsable for works.
Which format your demolition requires depends on the type of building, its size, whether a project under the Ley de Ordenación de la Edificación (LOE) is involved and what your town hall's ordinance says. There is no single national threshold we can quote for every municipality on the Costa del Sol; the exact criteria per town are (to be verified) with your técnico or the ayuntamiento.
What does the dirección facultativa do during the works?
The dirección facultativa is the technical team that directs the works on behalf of the owner. On a demolition its role includes checking that the works follow the documented method and approving the contractor's plan de gestión de residuos. When the documentation calls for it, the técnico visits the site at key moments – before the structure comes down, when party walls are exposed, at the end.
For an owner abroad, the dirección facultativa is your independent technical eyes on site. It is worth agreeing with your técnico in advance how often they will visit and how they report to you, separately from the photo updates the contractor sends.
When is a safety coordinator needed?
Under Real Decreto 1627/1997, when more than one company, or a company plus self-employed workers, take part in the works, the promotor appoints a coordinador de seguridad y salud for the execution phase. On a demolition that is common: a demolition contractor plus a RERA-registered asbestos company, or plus a separate haulier, already means several parties.
The promotor is the party commissioning the works – in a private demolition, normally the owner; confirm with your técnico who acts as promotor if the property belongs to several heirs or a company. The coordinator is frequently the same técnico who wrote the safety study, but it does not have to be. Our guide on health and safety on a Spanish demolition site covers this in detail.
What the contractor does – and does not – sign
A demolition contractor is not a substitute for the técnico. At Demoliciones Málaga we do not draft projects, do not sign technical reports and do not obtain licences. What we do:
- work from the project or technical documentation of your técnico;
- prepare our own plan de seguridad y salud from the safety study;
- prepare the plan de gestión de residuos for the waste we produce and hand over;
- coordinate dates and site visits with your architect;
- tell you which documentation a town hall usually asks for, so nothing is missing;
- hand over delivery receipts (justificantes de entrega) for all waste taken to an authorised facility.
Where asbestos is present, the RERA-registered company that works as our subcontractor prepares and files its own plan de trabajo; we coordinate the rest of the demolition around it. Details on that process are on our sister site, in the guide to who approves an asbestos work plan.
How to find and brief a técnico from abroad
Many foreign owners already have an architect for the new house. If not, a técnico can be found through the professional associations in Málaga, by recommendation from your notary or gestor, or through the contractor's network of contacts. Practical points when you brief them remotely:
- Send the property data: cadastral reference, nota simple, old plans if any, and what you plan to do with the plot.
- Ask them to check protection first: catalogue, protected setting, archaeological zone, historic centre. That decides between declaración responsable and licence.
- Agree the document scope: proyecto or memoria técnica, safety study type, waste study.
- Clarify who files and who pays municipal fees and the waste deposit.
- Agree reporting: how often they visit, in which language they report, how documents are signed remotely.
- Connect them with the contractor early, so the method in the documents matches the access and machinery actually possible on site.
If you are coordinating everything from abroad, our remote demolition management service explains how we keep the técnico, the RERA company and you in the loop.
Five misunderstandings about signatures and responsibility
Owners who have renovated property in other countries bring assumptions with them. These are the ones that cause trouble most often in Spain:
- “The demolition firm will sort out the paperwork.” Some may offer to; we do not, and in any case the declaración responsable is the owner's statement. If it is wrong, the owner answers for it.
- “A declaración responsable means no technical documents.” The procedure is lighter; the content is not. Ordinances such as Málaga city's ask for signed technical documentation.
- “The safety study is the contractor's job.” The study or basic study is part of the technical documentation; the contractor's plan is built from it, not instead of it.
- “Waste is the contractor's problem once it leaves the site.” The waste study sits in the project, the contractor prepares the management plan, and the owner needs the delivery receipts to recover the waste deposit. All three are linked.
- “Asbestos can be dealt with later.” Asbestos-containing materials are removed by a RERA-registered company before the general demolition, under a plan approved by the labour authority. Leaving it for later stops the job.
Clearing up these points at the start is the cheapest form of risk control on a demolition. A short call between owner, técnico and contractor before any document is drafted usually does it.
Examples: what documentation different jobs tend to involve
The following are typical patterns seen in the provincia de Málaga; the exact requirements always come from your técnico and town hall.
- Detached villa in an urbanización, unprotected. Declaración responsable with technical documentation, a safety study or basic study, a waste study and a road occupation permit for skips. See building demolition.
- Collapsed outbuildings on a rural finca. Often smaller in scale, but access, asbestos-cement roofs and the land classification complicate things. See finca demolition.
- Partial demolition of an extension while the main house stays. The documentation must cover the stability of what remains and the closing of the junction.
- Building in a Conjunto Histórico. Licence, heritage authorisation where applicable, and documentation that justifies the demolition from a heritage perspective.
The general permit logic is in our guide on licence or declaración responsable in Andalusia.
Sources
Frequently asked questions
Who signs a demolition project in Spain?
A técnico competente drafts and signs the technical documentation – proyecto or memoria técnica, safety study and waste study. The contractor does not sign these.
Which professional is the técnico competente?
It depends on the type of work and building. Your técnico or their professional association confirms who is competent for your demolition; we do not name a degree in general.
Is a memoria técnica enough for a small house?
In some cases, yes; Málaga city, for example, accepts a proyecto or a memoria técnica with a certificado técnico. The criteria in other towns are to be verified with your técnico or ayuntamiento.
What is the dirección facultativa?
The technical team directing the works on the owner's behalf; on a demolition it supervises the method and approves the contractor's plan de gestión de residuos.
Does the contractor prepare any documents?
Yes: the contractor prepares its plan de seguridad y salud from the safety study and its plan de gestión de residuos from the waste study.
When do I need a safety coordinator?
When several companies or self-employed workers take part, the promotor appoints a coordinador de seguridad y salud for the execution phase (Real Decreto 1627/1997).
Who is the promotor on a private demolition?
The party commissioning the works, normally the owner. With several heirs or a company as owner, clarify with your técnico who acts as promotor.
Who writes the asbestos work plan?
The RERA-registered company that removes the asbestos prepares and files its plan de trabajo with the provincial labour authority; on our jobs it is our subcontractor.
Can the contractor obtain the licence for me?
Not in our case: we do not file declarations or obtain licences. The owner and the técnico do, and we coordinate the works around their documents.
Can I sign documents remotely from abroad?
Many formalities can be handled remotely with electronic signature or a representative; your técnico or gestor explains which method works for your file.
Do I need a new project if I rebuild afterwards?
The new building is a separate procedure with its own project. Ask your architect whether the demolition can be documented together with it or separately.