In short
In Málaga city, the Ordenanza Municipal de Licencias Urbanísticas (OMLU), published in the BOP de Málaga on 30/12/2025, puts total and partial demolitions under a declaración responsable in urban land, rustic land and SAFO, and under a licence for protected buildings, protected settings and archaeological zones. The declaración needs a proyecto or memoria técnica signed by a técnico competente, a certificado técnico and photographs. Demolitions in the Centro Histórico also need prior authorisation from the regional heritage department.

Contents
- Which rules apply to a demolition in Málaga city?
- What does the OMLU say about demolitions?
- Which documents does a declaración responsable need in Málaga?
- What changes if a licence is required?
- Demolishing in Málaga's Centro Histórico
- How the works are organised once the file is ready
- Common mistakes owners make with a Málaga city demolition
- Country houses on rustic land inside the municipality
- What you can send us before the documents are finished
- Frequently asked questions
Which rules apply to a demolition in Málaga city?
Inside the municipality of Málaga the demolition procedure is governed by the regional framework (the LISTA and its Reglamento) and, at local level, by the Ordenanza Municipal de Licencias Urbanísticas (OMLU). The new OMLU was published in the Boletín Oficial de la Provincia de Málaga on 30 December 2025 and came into force the following day.
The municipal body that handles planning files is the Gerencia Municipal de Urbanismo (GMU). Owners abroad often deal with it only through their técnico, which is the sensible approach: the GMU's procedures, forms and electronic filing are designed for professionals and are entirely in Spanish.
The rest of this guide only covers Málaga city. Towns such as Torremolinos, Rincón de la Victoria or Marbella have their own ordinances, explained in our guide to demolition rules in other Costa del Sol towns.
What does the OMLU say about demolitions?
Annex I.1 of the OMLU lists the works and the procedure each one follows. Item 2, Demoliciones totales o parciales de edificaciones, sets out two routes:
| Where the building stands | Procedure in the OMLU |
|---|---|
| Urban land (suelo urbano) | Declaración responsable |
| Rustic land (suelo rústico) | Declaración responsable |
| SAFO, as the ordinance names this category | Declaración responsable |
| Protected buildings | Licencia urbanística |
| Protected settings (entornos) | Licencia urbanística |
| Archaeological zones | Licencia urbanística |
This mirrors the regional rule introduced in 2024: unprotected buildings by declaración responsable, protected ones by licence. Which category your plot belongs to is a question for your técnico, who reads it from the planning documents and the municipal catalogue. If the land classification is unclear – common with older properties on the edge of the city – settle it before preparing documents.
Which documents does a declaración responsable need in Málaga?
For a declaración responsable for works, Annex II.8 of the OMLU asks for a set of documents. For a demolition the core items are:
- Proyecto or memoria técnica signed by a técnico competente, describing the building and how it will be demolished.
- Certificado técnico, also signed by the técnico.
- A separate document if the works occupy the public road – for example a skip, a crane or a fenced area on the pavement.
- Photographs of the building.
Where the works involve a project under the Ley de Ordenación de la Edificación (LOE), an Estudio de Seguridad y Salud is also part of the file. Health and safety documentation exists for every demolition under Real Decreto 1627/1997; our guide on health and safety on a Spanish demolition site explains the difference between the study, the basic study and the contractor's plan.
What changes if a licence is required?
When the building is protected, in a protected setting or in an archaeological zone, the demolition is processed as a licencia urbanística instead. The GMU reviews the application before the works can start.
For licences for partial demolition, the OMLU asks for a nota simple registral less than three months old. Order it from the Registro de la Propiedad shortly before filing, not months in advance, or it will have expired by the time the file is complete. A protected building usually also comes with conditions on what must be kept, documented or dismantled by hand, which your técnico translates into the demolition method.
Demolishing in Málaga's Centro Histórico
The historic centre of Málaga is a Bien de Interés Cultural: the Conjunto Histórico was registered as BIC by Decreto 88/2012. Under GMU Instrucción 2025/04, any total or partial demolition there needs prior authorisation from the Consejería competente en Patrimonio Histórico, the regional heritage department, in addition to the municipal procedure.
In practice this means three things for an owner:
- The timeline is longer, because two administrations are involved.
- The technical documents must justify the demolition from a heritage point of view, not just describe the method.
- The works themselves are usually more manual: narrow streets, party walls shared with neighbours and limited space for machines favour hand demolition in sections, with materials taken out in small loads.
For interior-only work in a historic flat (removing partitions, kitchens or bathrooms) the questions differ; our sister site covers whether you need a permit to remove an internal wall.
How the works are organised once the file is ready
Once your técnico has filed the declaración responsable or obtained the licence, the demolition follows the documented method. Typical steps in a city setting:
- Utilities cut and certified by the supply companies, arranged by the owner.
- Site perimeter: fencing, protection of the pavement and, where neighbours share walls, propping or protection of the party walls as specified.
- Removal of hazardous materials first. Asbestos-cement elements are removed by a company registered in the RERA under its own approved plan de trabajo; on our jobs that company works as our subcontractor while we coordinate the rest.
- Selective dismantling: wood, metals, glass, plastics and gypsum separated before the structure comes down, as Ley 7/2022 requires.
- Structural demolition, manual, mechanical or combined depending on access and neighbours.
- Loading and removal of rubble to an authorised facility, with delivery receipts handed to the owner for the waste deposit refund.
Our service pages for building demolition and partial demolition describe how we execute each phase; our Málaga city page covers the districts we work in.

Common mistakes owners make with a Málaga city demolition
Most delays in Málaga city are not caused by the GMU but by a file that was started on the wrong assumption. The usual ones:
- Assuming the old licence rule still applies and waiting for a licence that is not needed – or the opposite, filing a declaración for a building that is in fact protected.
- Forgetting the road occupation document. In dense districts almost every demolition needs some use of the pavement for skips or lorries.
- An outdated nota simple for partial-demolition licences.
- No asbestos check. Uralita roofs on old annexes, sheds or terraces are common; discovering them mid-demolition stops the job until the RERA-registered company has done its part.
- Unclear ownership. Inherited properties with several heirs, some living abroad, need agreement on who acts as promotor before the técnico can file.
- Ignoring the neighbours. Where a building is under propiedad horizontal, the community must be informed before structural or façade elements are demolished, and works on common elements need the owners' meeting agreement.
If you are planning from abroad, our house and villa demolition page explains what we need from you for a quote and how we report progress with photos.
Country houses on rustic land inside the municipality
The municipality of Málaga is not only city blocks. On its outskirts there are older country houses, farm buildings and warehouses on rustic land, many of them inherited by families now living elsewhere in Spain or abroad. For these, the OMLU route is also a declaración responsable, provided the building is not protected – but the practical file looks different from a city-centre job.
- Land classification first. Whether the building is on urban land, rustic land or in SAFO decides which section of the ordinance your técnico works with, and old cadastral descriptions do not always match reality.
- Access and services. Rural tracks limit lorry size and turning space, which shapes the demolition method and the number of loads.
- More asbestos-cement. Farm annexes, water tanks and roofs from past decades frequently contain fibre-cement; plan the RERA-registered company's work before anything else.
- What happens next. If you want to build again on rustic land, the new construction is a separate and often more demanding question; ask your técnico before demolishing anything you might later want to keep.
Our finca demolition page explains how we approach rural plots.
What you can send us before the documents are finished
You do not need the finished file to ask for a quote. We can price a Málaga city demolition from:
- the address or cadastral reference and the district;
- photos of each façade, the roof, the interior and the street access;
- the approximate built area and number of floors;
- whether walls are shared with neighbours;
- any known uralita or fibre-cement elements;
- your target date and whether a new building will follow.
The quote lists the demolition method, waste handling and what is excluded. For the factors that move the price, see our sister site's guide to how a demolition quote is built.
Sources
Frequently asked questions
What is the GMU?
The Gerencia Municipal de Urbanismo is Málaga city's planning department. It processes declaraciones responsables and licences for works inside the municipality of Málaga.
When did the new Málaga licensing ordinance come into force?
The new OMLU was published in the BOP de Málaga on 30/12/2025 and entered into force the following day.
Do I need a licence to demolish a house in Málaga city?
Not if it is unprotected: the OMLU puts demolitions in urban land, rustic land and SAFO under a declaración responsable. Protected buildings, protected settings and archaeological zones need a licence.
Which documents does the declaración responsable need?
Annex II.8 asks for a proyecto or memoria técnica signed by a técnico competente plus a certificado técnico, a separate document if the public road is occupied, and photographs.
How old can the nota simple be?
For partial-demolition licences the OMLU asks for a nota simple registral less than three months old.
Is a health and safety study needed in Málaga?
Where a LOE project is involved the file includes an Estudio de Seguridad y Salud. Every demolition has a study or basic study under Real Decreto 1627/1997.
Can I demolish a building in the Centro Histórico?
Any total or partial demolition there needs prior authorisation from the Consejería competente en Patrimonio Histórico (GMU Instrucción 2025/04), on top of the municipal procedure. Expect a longer timeline.
Who files the documents with the GMU?
The owner, normally through their técnico. As contractor we work with the técnico's documentation and coordinate dates, but we do not file the declaración or obtain licences.
Do these rules apply to Torremolinos or Rincón de la Victoria?
No. The OMLU only applies inside the municipality of Málaga; neighbouring towns set their own documents and deadlines in their ordinances.
What if my building contains uralita?
The asbestos-cement elements are removed first by a RERA-registered company under its approved plan de trabajo; on our jobs it works as our subcontractor and we coordinate the rest of the demolition.
Can the skip stay on the street during the works?
Only with authorisation to occupy the public road; in the OMLU the road occupation is covered by a separate document in the file.